Change Orders FEGCA 3/8/06
RATIONALE/OBJECTIVE:

The approval of change orders to construction contracts will be done on a legal contract basis between the contractor and the Cobb County School District (District).

RULE:

Any change order in a construction contract shall be approved as follows:
    1. A change order in the amount of $25,000 or less shall be submitted to the Chief
        Operations Officer and the Director of Construction for approval. The Change order
        to be executed by the Superintendent or Designee.
    2. A change order in the amount of $25,001 thru $200,000 must be approved by
        Coordination Record and executed by the Superintendent or Designee.
    3. Board of Education (Board) Responsibilities:
        a. A change order in an amount greater than $100,000 shall be reported to the Board.
        b. A change order in an amount greater than $200,000 requires Board approval.

Reclassified an Administrative Rule: 9/1/04